Which option represents a basic Cost-Reimbursement contract type that reimburses costs?

Study for the Certified Professional Property Administrator (CPPA) Module 3 Test. Practice with questions that include hints and detailed explanations. Prepare efficiently and excel on your certification exam!

Multiple Choice

Which option represents a basic Cost-Reimbursement contract type that reimburses costs?

Explanation:
In cost-reimbursement contracts, the contractor is reimbursed for allowable costs actually incurred, plus a fee. The basic form is the straightforward one labeled Cost, because there’s no additional incentive structure attached. Time-and-Materials is a hybrid method that reimburses labor at stated rates plus materials at cost, so it isn’t the pure baseline reimbursement. Cost-Plus-Incentive-Fee and Cost-Plus-Award-Fee also reimburse costs but add incentive-based elements to the fee, which changes the compensation structure from the simple cost-reimbursement arrangement. Therefore, the option that represents the basic cost-reimbursement contract type is the one labeled Cost.

In cost-reimbursement contracts, the contractor is reimbursed for allowable costs actually incurred, plus a fee. The basic form is the straightforward one labeled Cost, because there’s no additional incentive structure attached. Time-and-Materials is a hybrid method that reimburses labor at stated rates plus materials at cost, so it isn’t the pure baseline reimbursement. Cost-Plus-Incentive-Fee and Cost-Plus-Award-Fee also reimburse costs but add incentive-based elements to the fee, which changes the compensation structure from the simple cost-reimbursement arrangement. Therefore, the option that represents the basic cost-reimbursement contract type is the one labeled Cost.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy